WINONA, Minn. – Firefighters spent four hours Monday at the Bay State Milling plant where the possibility spontaneous combustion from flour dust posed a major risk, according to their after-action report. This is from the report:

> Firefighters were summoned at 7:45 p.m. to the giant mill the foot of Franklin Street.

> Bay State employees told the first fire crew that there was a possible dust explosion in a storage bin on the seventh floor.

> A second crew followed an employee to the seventh floor to assess the situation.

> Smoke was coming from a vent pipe. A two-foot by two-foot manhole had been blown through a side of the tank.

 > All off-duty and part-time fire personnel were paged to report immediately to the scene.

> Another fire crew assessed the damage to identify possible access to the bin from the lower floors.

> When off-duty crews and part-time personnel arrived, the decision was made to flow water into the top of the tank and onto the smoldering flour.

> A 2-1/2 inch hose line with a spinning nozzle was lowered into the tank to cool the super-heating flour.

> Ductwork was followed from the bin to the dust collector to assure that all fire was extinguished.

> Five firefighters remained to 1:57 a.m. to assure extinguishment was complete.

Earlier: Fire crews intercept explosive dust at Bay State

ScWNA bay state millg - Winona Journal

Bay State Milling. 55 Franklin Street. Produces wheat, rye, oat, seeds, spices and other milled products.

2023 10 02 bay state niillg crews - Winona Journal

All hands called. When fully staffed, the Fire Department roster includes 21 full-time and 30 part-time positions. A shift consists of six captains and 12 firefighter-drivers. Of those 12 firefighters, nine are paramedics. Image: Winona Fire Department